单个项目中的多条关键路径

卡莉Chaput
卡莉Chaput ✭✭
编辑06/09/23 内容基本知识

我的项目计划中的最后一个任务/活动不是项目的“结束”,或者至少不是我们关心的报告目的的结束。

我在制药公司工作,我们的项目表跟踪他们的NDA提交,这是项目的“结束”,当涉及到执行报告和进度监控时,每个人都关心。在此日期之后,实际上会有数年的活动,包括补充NDA提交,一旦第一次提交完成,补充NDA提交将有效地成为新的“结束”。

当我现在使用“显示关键路径”选项时,没有任何东西被突出显示,因为没有任何东西与项目计划中的最终日期联系在一起,我试着在gantt中使用“显示行驶路径”选项,这几乎是无用的,因为薄的暗紫色高光在灰色的衬托下几乎不明显。

我点击了我能找到的所有设置,但没有看到任何方法可以让这条车道的高亮显示更好的颜色,除了甘特,高亮也没有显示在任何地方,如果能在网格中看到这一点,那就太好了。

在这一点上,我正在考虑创建一个名为“至关重要”的专栏,并将其作为一个手动下拉列表,我们可以将活动分类为对特定里程碑至关重要的活动,但这样做的明显问题是,由于它将是手动添加的,因此可能会错过实际上在关键路径上的事情。


是否有任何工作可以突出显示多个关键路径或手动指定关键路径应该关注的“终点”?

否则,有没有办法改变驾驶路径的颜色(包括照片)或建议我如何改进专栏的想法?

驱动路径highlight.JPG


答案

Hi @clawson<\/a> <\/p>

The Jira Connector would need to be purchased in addition to your Smartsheet plan. If your plan doesn't include this connector, you can contact the Sales team from this page. <\/a><\/p>

Here's more information: Smartsheet for Jira Connector: Overview<\/a><\/p>

Cheers,<\/p>

Genevieve<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":343,"name":"Add Ons and Integrations","url":"https:\/\/community.smartsheet.com\/categories\/apps-and-integrations","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[]},{"discussionID":106634,"type":"question","name":"Formula to set the Task Health.","excerpt":"Hi Good Morning, I have a question on this formula. Can you tell me what I did wrong please? Thanks for your great help.","categoryID":321,"dateInserted":"2023-06-20T14:28:24+00:00","dateUpdated":null,"dateLastComment":"2023-06-21T14:04:40+00:00","insertUserID":162441,"insertUser":{"userID":162441,"name":"AAL","title":"Automation - Record a Date","url":"https:\/\/community.smartsheet.com\/profile\/AAL","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-21T15:13:51+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":45516,"lastUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-06-21T15:10:43+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":12,"countViews":71,"score":null,"hot":3374634784,"url":"https:\/\/community.smartsheet.com\/discussion\/106634\/formula-to-set-the-task-health","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/106634\/formula-to-set-the-task-health","format":"Rich","tagIDs":[254],"lastPost":{"discussionID":106634,"commentID":381484,"name":"Re: Formula to set the Task Health.","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/381484#Comment_381484","dateInserted":"2023-06-21T14:04:40+00:00","insertUserID":45516,"insertUser":{"userID":45516,"name":"Paul Newcome","title":"","url":"https:\/\/community.smartsheet.com\/profile\/Paul%20Newcome","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/082\/nQPUTVFKKWDJ2.jpg","dateLastActive":"2023-06-21T15:10:43+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Using Smartsheet","url":"https:\/\/community.smartsheet.com\/categories\/using-smartsheet"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"image":{"url":"https:\/\/us.v-cdn.net\/6031209\/uploads\/Y9UHM44PUCBT\/image.png","urlSrcSet":{"10":"","300":"","800":"","1200":"","1600":""},"alt":"image.png"},"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-20T18:05:21+00:00","dateAnswered":"2023-06-20T17:22:23+00:00","acceptedAnswers":[{"commentID":381355,"body":"

Happy to help. 👍️<\/span><\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"}]},{"discussionID":106616,"type":"question","name":"Groups - how many users in a group?","excerpt":"The help files indicates you can bulk upload 1,000 emails to a group. Is that the maximum number of users that can be in a group? I could not find documentation indicating how many users could be in a group. TIA","categoryID":321,"dateInserted":"2023-06-19T21:51:09+00:00","dateUpdated":"2023-06-20T08:19:00+00:00","dateLastComment":"2023-06-20T09:36:32+00:00","insertUserID":15741,"insertUser":{"userID":15741,"name":"ker9","url":"https:\/\/community.smartsheet.com\/profile\/ker9","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-20T23:25:59+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭✭"},"updateUserID":91566,"lastUserID":91566,"lastUser":{"userID":91566,"name":"Genevieve P.","title":"Community Manager","url":"https:\/\/community.smartsheet.com\/profile\/Genevieve%20P.","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/KHY4Y67W0VRX\/nF76D5N9MFB28.png","dateLastActive":"2023-06-21T15:23:57+00:00","banned":0,"punished":0,"private":false,"label":"Employee Admin"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":1,"countViews":30,"score":null,"hot":3374465861,"url":"https:\/\/community.smartsheet.com\/discussion\/106616\/groups-how-many-users-in-a-group","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/106616\/groups-how-many-users-in-a-group","format":"Rich","tagIDs":[442],"lastPost":{"discussionID":106616,"commentID":381246,"name":"Re: Groups - how many users in a group?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/381246#Comment_381246","dateInserted":"2023-06-20T09:36:32+00:00","insertUserID":91566,"insertUser":{"userID":91566,"name":"Genevieve P.","title":"Community Manager","url":"https:\/\/community.smartsheet.com\/profile\/Genevieve%20P.","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/userpics\/KHY4Y67W0VRX\/nF76D5N9MFB28.png","dateLastActive":"2023-06-21T15:23:57+00:00","banned":0,"punished":0,"private":false,"label":"Employee Admin"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Using Smartsheet","url":"https:\/\/community.smartsheet.com\/categories\/using-smartsheet"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-20T11:01:39+00:00","dateAnswered":"2023-06-20T09:36:32+00:00","acceptedAnswers":[{"commentID":381246,"body":"

Hi @ker9<\/a> <\/p>

That limit is specific to bulk-uploading the emails into the group, to ensure that the request is processed successfully. I don't believe there's currently a hard limit for the number of users that can be in a group. I have seen some groups with around 10,000 contacts, if that helps. <\/p>

Cheers,<\/p>

Genevieve<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":442,"urlcode":"groups-and-group-management","name":"Groups and Group Management"}]}],"initialPaging":{"nextURL":"https:\/\/community.smartsheet.com\/api\/v2\/discussions?page=2&categoryID=341&includeChildCategories=1&type%5B0%5D=Question&excludeHiddenCategories=1&sort=-hot&limit=3&expand%5B0%5D=all&expand%5B1%5D=-body&expand%5B2%5D=insertUser&expand%5B3%5D=lastUser&status=accepted","prevURL":null,"currentPage":1,"total":5390,"limit":3},"title":"Trending in Using Smartsheet","subtitle":null,"description":null,"noCheckboxes":true,"containerOptions":[],"discussionOptions":[]}">

使用Smartsheet的趋势