Hi,
I have an action plan with an action column, a delay column, a referent column, and a progress column.
I would like to create a workflow that sends a notification (mail) to the referent of the action 3 days before the date entered in the column "delay" if the progress is not "finished" in order to remind him to finish the action.
这是我的审判,但是它将发送notifications only for actions that have a deadline = to the current date
Translation :
Statut = progress of the action
Délai = delay
If somone have the solution, thanks !
Comments
-
Andrée Starå ✭✭✭✭✭✭
Hi Thibault,
You were almost there!
- If you changeonafter Run once to3 days before
- Delete the second Condition
That should work.
Did it?
I hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant / CEO @ WORK BOLD
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
-
Hi Andrée,
It works, thank you for your message and sorry for my late feedback.
Regards.
-
Andrée Starå ✭✭✭✭✭✭
Excellent!
Happy to help!
✅Did my post help answer your question or solve your problem? Please help the Community bymarking it as the accepted answer. It will make it easier for others to find a solution or help to answer!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå| Workflow Consultant / CEO @WORK BOLD
W:www.workbold.com| E:[email protected]| P: +46 (0) - 72 - 510 99 35
Feel free to contact me about help with Smartsheet, integrations, general workflow advice, or something else entirely.
Categories
Hi @Jagdeep<\/a> - Unfortunately, my experience has been that Datamesh \"Immediate\" can take up to 5 minutes (perhaps more).<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":321,"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":219,"urlcode":"Sheets","name":"Sheets"},{"tagID":334,"urlcode":"automations","name":"Automations"},{"tagID":381,"urlcode":"DataMesh","name":"DataMesh"}]},{"discussionID":106941,"type":"question","name":"How to show data of previous working day?","excerpt":"For a stacked column chart on a dashboard, I count the number of applicable cases daily. The current formula shows NO DATA on Monday because TODAY(-1) is Sunday. =COUNTIFS({Customer Escalation Region}, $Region@row, {Customer Escalation Request Reason}, \"Close Gap\", {Customer Escalation Request Date}, TODAY(-1)) I'm…","snippet":"For a stacked column chart on a dashboard, I count the number of applicable cases daily. The current formula shows NO DATA on Monday because TODAY(-1) is Sunday.…","categoryID":321,"dateInserted":"2023-06-27T10:29:20+00:00","dateUpdated":null,"dateLastComment":"2023-06-27T12:02:55+00:00","insertUserID":162184,"insertUser":{"userID":162184,"name":"Sachiko Kagami","title":"Customer Service Manager","url":"https:\/\/community.smartsheet.com\/profile\/Sachiko%20Kagami","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-27T12:25:47+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":151203,"lastUser":{"userID":151203,"name":"Nick Korna","url":"https:\/\/community.smartsheet.com\/profile\/Nick%20Korna","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-27T12:11:22+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":3,"countViews":23,"score":null,"hot":3375730935,"url":"https:\/\/community.smartsheet.com\/discussion\/106941\/how-to-show-data-of-previous-working-day","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/106941\/how-to-show-data-of-previous-working-day","format":"Rich","lastPost":{"discussionID":106941,"commentID":382502,"name":"Re: How to show data of previous working day?","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/382502#Comment_382502","dateInserted":"2023-06-27T12:02:55+00:00","insertUserID":151203,"insertUser":{"userID":151203,"name":"Nick Korna","url":"https:\/\/community.smartsheet.com\/profile\/Nick%20Korna","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-06-27T12:11:22+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Using Smartsheet","url":"https:\/\/community.smartsheet.com\/categories\/using-smartsheet"},{"name":"Smartsheet Basics","url":"https:\/\/community.smartsheet.com\/categories\/smartsheet-basics%2B"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-06-27T11:47:48+00:00","dateAnswered":"2023-06-27T11:40:22+00:00","acceptedAnswers":[{"commentID":382497,"body":" Hi @Sachiko Kagami<\/a>,<\/p> The WORKDAY function is what you're after here.<\/p>