Create and work with a Gantt chart
Maximize the Gantt View when reviewing or working on your project management tasks in a sheet or report.
When you switch your sheet or report to Gantt View, tasks appear as bars in a timeline. You see the duration, the start date, and the finish date of your project tasks asproject sheet columns.
Apart from that, you can also track the following:
- View Dependencies and track the relationship between tasks.
- View your project's Critical Path.
- Display the % Complete of your tasks.
- Use Hierarchy to create summary rows for further organization of your projects.
Add a Gantt chart
Before you add a Gantt chart
Make sure your sheet or report has at least two Date columns.
The columns you add must represent the start date and the end date of your tasks. The length of a task bar represents the span of time between those dates. This is why you need at least twoDatecolumns; otherwise, you cannot switch to Gantt View.
The Gantt View does not recognizeDatecolumns with aColumn Formulaapplied. If you need your dates to autofill rows, use theCell Formula and Autofillfeatures instead. You could also set up column formulas and use a report to display your Gantt chart.
To add a Gantt chart
- In the toolbar, selectGantt Viewto switch your view.
The chart appears to the right of your columns. There is also a divider that separates the grid columns from the Gantt chart.
To widen the display of either section:
- Hover your pointer over the divider.
- When you see thecolumn resize pointer
, drag the divider to the right or left.
Edit your Gantt chart
- In the upper right area of the sheet, selectEdit Project Settings.
- Modify theProject Settingsin each tab according to your project needs:
- Dependency Settings
- Timeline Display
- Resource Management
Adjust the timeline display
In theProject Settingsdialog, you can modify the units of time you see in the Gantt chart.
一个更简单的方法是通过使用Zoom InandZoom Out
buttons in the toolbar.
Organize your project tasks
Use row hierarchies in Gantt charts to organize rows into sections or phases.
When you use row hierarchies, child rows display as individual task bars in the Gantt chart based on their start and end dates. If you turn onDependencieson the sheet, parent rows reflect a summary of their child rows.
The parent row values are calculated automatically in the following columns:
- Duration
- Start DateandEnd date
- % Complete
You cannot modify parent values. If dependencies are off, you can change the parent row information as needed.
Other tips in editing your Gantt chart
- Configure a% Completecolumn in theProject Settingsdialog. Any time you enter a value in this column, you see it indicated in the task bar.
- Apply colorto the task bars.