Hi dear community,
I need a formula to return the values "Process" and "At Risk" when a certain date is reached.
I have a "Start date" column. I need to notify the assignee of the status for each task (all in separate columns). When we are 145-91 days from the start date, it should return "Process". When we are 90-0 days from the start date it should return "At Risk".
I tried the following mini formulas, which work. But I don't know how to combine them into one formula.
=IF([Start Date]@row - 91 > TODAY(), "At Risk")
=IF([Start Date]@row - 145 > TODAY(), "Process")
Any help would be greatly appreciated!
Best Answer
-
Paul Newcome ✭✭✭✭✭✭
Try this:
(开始日期)=如果(@row > =今天(-90),“在Risk", IF([Start Date]@row>= TODAY(-145), "Process"))
Answers
-
Paul Newcome ✭✭✭✭✭✭
Try this:
(开始日期)=如果(@row > =今天(-90),“在Risk", IF([Start Date]@row>= TODAY(-145), "Process"))
-
Haleh ✭
Thank you!
-
Paul Newcome ✭✭✭✭✭✭
Help Article Resources
Categories
Check out theFormula Handbook template!
HAS() will only return true under three conditions.<\/p>
- The cell is a multicontact cell and contains a match for the contact<\/li>
- The cell is a multiselect dropdown and contains a match<\/li>
- The cell is not a multicontact or multiselect dropdown and contains ONLY and EXACTLY the text you are matching against. <\/li><\/ol>
I am assuming your row in question is a standard Text\/Number cell? If so, you will need to get somewhat creative with some CONTAINS() statements.<\/p>
This will narrow down your matches to only cells that contain a space both before and after TAC. If, however, TAC can appear as the first or last \"word\" in the cell, it would not match in that circumstance as there would only be a space on one side.<\/p>
=IF(CONTAINS(\" TAC \", [Column Name1]@row), 1, 0)<\/p>
<\/p>If TAC can appear as the first or last \"word\" in the cell, this will cover those possibilities as well.<\/p>
=IF(OR(CONTAINS(\" TAC \", [Column Name1]@row), LEFT([Column Name1]@row, 4) = \"TAC \", RIGHT([Column Name1]@row, 4) = \" TAC\"), 1, 0)<\/p>
<\/p>If it is possible that TAC will be the exact entry of the cell, you will need an additional statement to cover that, as there would not be spaces on either side. This will add that option.<\/p>
=IF(OR(CONTAINS(\" TAC \", [Column Name1]@row), LEFT([Column Name1]@row, 4) = \"TAC \", RIGHT([Column Name1]@row, 4) = \" TAC\", [Column Name1]@row = \"TAC\"), 1, 0)<\/p>
<\/p>If there are other situations you may have in your sheet, i.e., TAC inside parenthesis, or before or after punctuation, etc, you will additional statements to include those options as well.<\/p>"}]}},"status":{"statusID":3,"name":"Accepted","state":"closed","recordType":"discussion","recordSubType":"question"},"bookmarked":false,"unread":false,"category":{"categoryID":322,"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions","allowedDiscussionTypes":[]},"reactions":[{"tagID":3,"urlcode":"Promote","name":"Promote","class":"Positive","hasReacted":false,"reactionValue":5,"count":0},{"tagID":5,"urlcode":"Insightful","name":"Insightful","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":11,"urlcode":"Up","name":"Vote Up","class":"Positive","hasReacted":false,"reactionValue":1,"count":0},{"tagID":13,"urlcode":"Awesome","name":"Awesome","class":"Positive","hasReacted":false,"reactionValue":1,"count":0}],"tags":[{"tagID":254,"urlcode":"Formulas","name":"Formulas"}]},{"discussionID":109170,"type":"question","name":"COUNTIFS formula with 3 criteria (2 of the criteria have formulas)","excerpt":"Hi - I am trying to create a COUNTIFS formula using three criteria in the same sheet - Status (I just want to count the Open items), Impacted IT Projects (which is another dropdown of project names to select from), and Severity (this column displays a \"High\", \"Medium\", or \"Low\" value based on the calculated score in column…","snippet":"Hi - I am trying to create a COUNTIFS formula using three criteria in the same sheet - Status (I just want to count the Open items), Impacted IT Projects (which is another…","categoryID":322,"dateInserted":"2023-08-18T20:29:26+00:00","dateUpdated":null,"dateLastComment":"2023-08-18T21:13:12+00:00","insertUserID":165367,"insertUser":{"userID":165367,"name":"Shari D","url":"https:\/\/community.smartsheet.com\/profile\/Shari%20D","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/defaultavatar\/nWRMFRX6I99I6.jpg","dateLastActive":"2023-08-18T21:12:12+00:00","banned":0,"punished":0,"private":false,"label":"✭"},"updateUserID":null,"lastUserID":163506,"lastUser":{"userID":163506,"name":"JamesB","title":"IT Project Manager","url":"https:\/\/community.smartsheet.com\/profile\/JamesB","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/avatarstock\/nEQMY42MFGXWS.png","dateLastActive":"2023-08-18T21:34:29+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"},"pinned":false,"pinLocation":null,"closed":false,"sink":false,"countComments":10,"countViews":95,"score":null,"hot":3384789758,"url":"https:\/\/community.smartsheet.com\/discussion\/109170\/countifs-formula-with-3-criteria-2-of-the-criteria-have-formulas","canonicalUrl":"https:\/\/community.smartsheet.com\/discussion\/109170\/countifs-formula-with-3-criteria-2-of-the-criteria-have-formulas","format":"Rich","lastPost":{"discussionID":109170,"commentID":391505,"name":"Re: COUNTIFS formula with 3 criteria (2 of the criteria have formulas)","url":"https:\/\/community.smartsheet.com\/discussion\/comment\/391505#Comment_391505","dateInserted":"2023-08-18T21:13:12+00:00","insertUserID":163506,"insertUser":{"userID":163506,"name":"JamesB","title":"IT Project Manager","url":"https:\/\/community.smartsheet.com\/profile\/JamesB","photoUrl":"https:\/\/us.v-cdn.net\/6031209\/uploads\/avatarstock\/nEQMY42MFGXWS.png","dateLastActive":"2023-08-18T21:34:29+00:00","banned":0,"punished":0,"private":false,"label":"✭✭✭✭"}},"breadcrumbs":[{"name":"Home","url":"https:\/\/community.smartsheet.com\/"},{"name":"Get Help","url":"https:\/\/community.smartsheet.com\/categories\/get-help"},{"name":"Formulas and Functions","url":"https:\/\/community.smartsheet.com\/categories\/formulas-and-functions"}],"groupID":null,"statusID":3,"attributes":{"question":{"status":"accepted","dateAccepted":"2023-08-18T21:12:26+00:00","dateAnswered":"2023-08-18T21:01:48+00:00","acceptedAnswers":[{"commentID":391499,"body":"