Navigate the project page in Resource Management

APPLIES TO

  • Resource Management

The project page is the area where you can see all the details associated with the project. We encourage building out the high-level details using the project schedule and the Project worklist, then handling adjustments to project assignments on the schedule.

Use project brief to build and manage projects

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

All licensed users can see the project brief for projects they are a part of.

From the project page, you can:

  • Set aproject budgetin time, fee, or expenses (non-labor costs). This is your estimated goal to meet your targeted profitability or deadline.
  • Add people to the project and create a work plan that fits the estimated budget.
  • Create work items and assign project responsibilities and due dates to your team.
  • View real-time progress of the project and monitor your budget.
  • Use quick links to projectreportsto analyze the data behind the work progress

Project brief

The project brief is the landing page to the project. The project brief displays an updated synopsis of the project. It shows the project description, people currently working on the project, a visualization of the project timeline, and progress of current work. All project properties are also visible on this page. The project brief updates automatically to constantly reflect the progress of the project.

The project brief includes:

  • Client name
  • Project name
  • Project start and end dates
  • Project owner
  • Project description (up to 2,048 characters, including line breaks)
  • Clickable links contained in the description

Project status and reports

Status for the project’s work, time, and fees appear on the left side of the project page brief. The show dropdown filters what data is displayed in this menu pane.

You can see information about:

  • 整个项目(默认)
  • Non-phase specific
  • Specific phase

Quick links to the time + fees and budget reports are at the bottom of the left pane.

You can use project brief in weekly team meetings as an agenda, and a way to record and clearly communicate each person's responsibilities.

Schedule

The schedule displays project phases and people scheduled to work on the project. Click anywhere on this schedule to access theproject scheduletab. Right click (or ctrl + click) to save the schedule image for sharing with your team or other key stakeholders.

Worklist

Worklist shows. This section shows the current project status, phases, team members, the team members percent allocation, work items, the project assignment dates, and status of each assignment.

Manage the project schedule

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

Resourcing Administrators, Portfolio Editors, People Schedulers, and Project Editors can manage a project’s schedule.

You can edit the project timeline and any associated assignments. You can create phases and assignments, and see the impact of those changes on the project's time and fee status.

By default, the schedule auto-zooms to fit the length of your project. Use the sliders at either end of the phase or assignment bars to change dates.

This image shows an example project schedule view.

Adding items to the project schedule

To add phases:

  1. Click the schedule where you'd like the phase to begin and then selectAdd Phase.
  2. Choose from one of the default phase names, or create a new phase name. The phase automatically extends to the end of the project, but you can edit it as needed.

To add assignments:

  1. Click anywhere on an empty date slot or phase and then selectAdd Team Member.
  2. Select a team member from the list. You can also choose a placeholder if you don't have a resource in mind. The assignment starts on the current day (or the project start date if it’s in the future) and extends to the end of the project or phase, but you can edit it as needed.

To add descriptions of work:

  • To add work to an existing assignment, click on a team member's assignment and then chooseWork Item. Enter your details in the text box.
  • 添加一个description of work when without assigning it to a team member, click anywhere on a blank portion of the schedule and selectAdd Work Item. Enter in text to create a new work item that starts on the current day (or the project start date if it’s in the future) and extends to the end of the project.

Manage tasks and assignments with the project worklist

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

Resourcing Administrators, Project Managers, and People Schedulerscan use the project worklist to manage tasks and assignments but cannot create Worklists.

Before you can use the Worklist, you mustset up a project.

Phases

Phasesbreak a project into different kinds of work. Add phases first, then add Work Items to each phase.

To add phases to worklist:

  1. At the top left of theWorklist, selectPhase. A new phase row appears at the bottom of the Worklist.
  2. Name the Phase. Use theEnterkey to add more phases; select anywhere on the screen when you’re done.
  3. To edit the Phase, select the new row. The properties pane opens in the right sidebar.

To adjust phase dates:

  1. Select the start or end date on a phase row to open the calendar.
  2. Select the new dates from the calendar.

Set the dates for each phase as you create them; the next phase you add will start immediately after the previous phase ends.

Adding work items to the worklist

Work Itemsdefine project deliverables, expectations, and responsibilities for the project, phase, or person.

To add work items:

  1. Hover over a person, then selectWork Item.
  2. In the right pane, fill out theWork Item properties.

Hovering over a row activates+ Work Itemat the bottom of the project or phase grouping so you can add details about the item.

分配工作项:

  1. Select the Work Item row to open the Work Item details.
  2. SelectAssign Team Member.

Or:

  • Hover over the Work Item and then selectAssign.

Copying work items in the worklist

You can duplicate aWork Item, copying it to either the project or a phase in the project. Copy Work Items when:

  • You have multiple people working on the same thing. Copy the Work Item multiple times and assign each copy to the people working on it.
  • You have similar assignments across many project phases, for example, a design review. Copy the Work Item for each phase and edit the dates.
  • You need to move a Work Item. Copy the Work Item to the new phase and delete the old Work Item.

To copy a work Item:

  1. On theWorklist, select theWork Itemyou want to copy.
  2. At the bottom of the right details pane, selectCopy.
  3. Select the project or phase where you want to copy the Work Item.

Deleting work items from the worklist

OnlyAdministrators and Project Managerscan delete Work Items. Deleting a Work Item deletes the entire row and all its contents, including the assignment. Time already tracked to the assignment is not deleted.

  1. Select theWork Item row.
  2. At the bottom of the right pane, select删除.

Adding people to the worklist

To add a team member to a phase:

There are two ways to add a Team Member to the Worklist:

  • Select the project or phase, then select+ Add Team Memberfrom the right panel.
  • Hover under the last phase or project entry and selectTeam Member. Your team directory appears in the right panel.

To add a team member to multiple phases:

  1. At the top of theWorklist, selectTeam Member.
  2. In the right panel, select thePhasesyou want to add team members to. You can also select the whole project.
  3. At the bottom of the panel, selectAdd Phases.
  4. Select theTeam Memberyou want to add.

All assignments have start and end dates. Depending on whether the person is assigned at the project or phase level, assignments will inherit the project or phase start and end dates by default.

Specifying work status in the worklist

You can specify a status for each Work Item. Administrators, Project Managers, and the person assigned to the work can change status throughout a project.

Use status to identify items that need attention. You can customize status settings to suit your organization’s unique vocabulary.

Status appears wherever a Work Item appears. For more information, seeWork Status.

Shifting dates in the worklist

Project and phase dates change. If you have defined phases and assignments, you can shift dates without editing each item.

To shift dates:

  1. In theWorklist, select the project or phase name. It’s in bold at the top of the project or phase section.
  2. In the right pane, selectShift Dates.
  3. Enter a new start date and then selectSave

Shifting a project moves all phases, assignments, and task due dates.

About work items

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

Resourcing Administrators, Portfolio Editors, People Schedulers, and Project Editors can add work items.

Work items are dependent on assignments. When you add a work item to a person's project assignment, the item appears on the today view of their personal page.

You can add work items in two places:

  • Project schedule: add unassigned work (at the project or phase-level) or add work to an existing team member's assignment.
    • Schedule tab > projects view
  • Project worklist: Add unassigned work (at the project or phase-level) or add work to an existing team member's assignment.
  • Project page >Worklisttab >+Work Item

Stay informed with notifications and the activity feed

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

Resourcing Administrators can adjust notification settings for the entire account. All other users can adjust their individual notification settings if notifications are enabled on the account.

Notifications can help you:

  • Know the status of your assignments or tasks
  • Know if a project you’re tracking has any changes
  • Get the rundown on what’s happened during the day

The Activity feed aggregates these important changes and displays them in a historical timeline on each project page and on your personal page.

Activity feed

The Activity feed is a record of key project changes. It shows changes to people, projects, and assignments. Each change appears with a time and date stamp.

The Activity feed is only available in English.View Resource Management in different languages.

Email notifications

Email notifications alert you about important changes to your assignments or projects. Notifications are smartly aggregated, meaning if you make multiple changes close together, they're all sent in one email to reduce inbox noise. You can also choose to receive a daily digest of the day’s activity.

Some email notifications are only available in English.View Resource Management in different languages.

Edit your personal notification settings

To change how often you receive notifications:

  1. SelectSettingsin the top right corner
  2. SelectMy Preferencesfrom the drop-down list
  3. In theNotification Preferencessection, select any of these options:
    • Off: No email notifications. You can still see changes in your Activity feed.
    • Immediately: Notifications go out as soon as changes are made. When multiple changes occur in a short time period, they’ll be grouped and sent in one email.
    • Daily (default): You’ll receive an email each morning detailing changes made during the past 24 hours.

Project notifications

By default, notifications are enabled for all projects.

If you’re resourcing or planning a tentative project and don’t want to alarm or overload your team with notifications, Resourcing Admins and Portfolio Editors can mute notifications on theProject Settingspage.

Following a project

You can follow the projects you’re not assigned to and get updates in your personal Activity Feed. If you're set to do so, you'll also receive email notifications about project changes.

To follow a project

  1. Go to theProjects页面,打开一个项目。
  2. Select theActivitytab.
  3. At the top of theActivityfeed, toggle on theFollowoption.

Edit account-wide notifications settings

电子邮件在您的帐户的通知人enabled by default.

If you’re a Resourcing Admin, you can set preferences in the Notifications section of theAccount Settingspage. Only Resourcing Admins can change notification preferences for allactive people.

There are two account-wide notifications settings:

  • Enable Notifications: Notifications go to all people in your account. Each person can still set their own email notification preferences from theirMy Preferencespage.
  • Disable Notifications: Disables notifications for all people in your account and hides email notification preferences from theMy Preferencespage.

Set up project templates

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

Resourcing Administrators, Portfolio Editors, and Project Editors can set up project templates.

Create a template project like any other project.

Use naming conventions that make it clear the project is a template. For example:

  • Project Name = TEMPLATE: X-Project
  • Project Type = Tentative
  • Project Tag = TEMPLATE

Once the template is set up, you can duplicate it to create a new project.

To duplicate a project:

  1. Go to the template's project page and selectProject Settings.
  2. On the left sidebar, selectCreate a Copy.

This image shows project settings and the pop out box to create a copy of a project.

If you have repeat projects with the same client, create a template project with the bill rates you charge that client and label it accordingly. Save it as anInternalorTentative项目类型,所以很明显只是一个模板。Now, you can copy this project every time you need that specific rate card.

Transfer time from one project to another

APPLIES TO

  • Resource Management

RELATED CAPABILITIES

Who can use this capability?

Resourcing Administrators, Portfolio Editors, and Project Editors can edit custom fields and tags on a project.

To transfer historical time tracked from one project to another, you can gather the total amount of hours for each person in the first project and create a new project. In the new project you will add each person with the total number of hours they worked in the old project and change the date in which they worked on the project to a date in the past.

Alternatively, you cantag projectswith the same custom field or tag, so when you view the schedule or reports, you can filter to see data associated with all projects with that tag or custom field.

You cannot merge projects in Resource Management.