Applies to
- Pro
- Business
- Enterprise
Capabilities
Who can use this capability
The sheet's老板andAdminscan enable dependencies to display the critical path.
Anyone shared to the sheet withEditoror higher-level permissions can choose to display or hide the critical path.
Track the critical path in a project
Track key tasks in your project by setting it up to display the critical path. As task dates or predecessor relationships change, this can impact the project's critical path. Smartsheet automatically updates and highlights the tasks on the current critical path.
What is critical path?
你的关键路径最长的distance between the start and the finish dates of your project, including all the tasks and their duration, which gives you a clear picture of the project’s actual schedule.
After you set up the critical path, you canapply a filterto only display tasks in the critical path.
Set up a sheet to display the critical path
To use critical path, your sheet must be inGantt View.
- Enable dependencies on the sheet by right-clicking any column header and selectingEdit Project Settings.
- Set up tasks in the sheet with dates and duration values that represent the shortest amount of time the task may take.
- For the critical path to be useful, use thePredecessorscolumn to define relationships between tasks (finish-to-start works best with critical path).
- Click thecritical pathicon in the upper-right of the sheet.
All tasks and milestones that make up the project's critical path appear highlighted in red in theGanttchart.